Four SpaceX items on 13 Nov. (1) The SpaceX website announced on 12 Nov, confirmed the same day by the NYT, Bloomberg and Reuters, two supercomputing campuses totalling $74 billion or more.

Read more

The Texas Starport campus is $24 billion or more and builds its own gas power plant, so it does not draw on the public grid (a Texas environmental filing of 11 Nov shows about 35 turbines and about 748 MW). The Arizona Cochise County campus is about $50 billion on 747 acres, with up to 9 compute buildings in 4 phases of 1.5 GW each, or 6 GW at full build. It is paired with 24 GWh of storage and about $3.6 billion of power infrastructure, uses dry cooling and pumps no industrial groundwater. A county public hearing is set for December. The logic: 6 GW scales the AI segment up by an order of magnitude, capex pressure stays on free cash flow, the Anthropic renewal is still undecided (our brief of 12 Nov), and finding tenants for the new capacity is the key question. Both sites pre-empt local backlash over water and power, but approval risk is near-term, with the Arizona hearing and the Texas tax abatement review on 9 Dec. Note that this is a company website announcement only: there is no new 8-K since 6 Nov, so the dollar figures and phasing are not yet confirmed in SEC filings. (2) On 12 Nov Zelensky said the 100 mph (161 km/h) speed cap on military Starshield is back. SpaceX told Axios this is false and nothing has changed. Zelensky described systematic limits over several days, not random outages, saying interceptors against Russian jet drones cannot reach the required speed. The timing coincides with a US special envoy arriving in Moscow. On 24 Oct Ukraine had confirmed that speeds were restored (a stable connection above 400 km/h). It is unclear who is actually imposing the limit, but political risk on the government and defence business is amplified again. It is the same storyline as the UK telecom pause and the EU trust warning (brief of 11 Nov). (3) United Airlines said on 12 Nov that Starlink now covers 50% or more of its daily flights. Its official tracker (as of 9 Nov) shows 689 aircraft equipped, about 45% of the planned fleet and about 54% of daily flights. The regional fleets are complete (100 CRJ-550 and 252 E175). The A321 family is 88% done, the 737 62% and the 737 MAX 19%, while the widebody long-haul fleet is essentially untouched. The year-end 2026 target is about 64% of flights and the full fleet by year-end 2027. The logic: scaling aviation revenue waits on the widebody long-haul fleet, which only arrives in 2027. (4) Starship Flight 15 has a launch window at 06:45 Singapore time on 14 Nov. It flies Booster 22 and Ship 42 (Gen 3 configuration) and deploys 26 Starlink V3 satellites over about 14 orbits and a flight of 22 hours or more, with a return the next day. It is the first attempt to catch both booster and ship with the tower. The logic: success would be the first full return of an orbital rocket, and the V3 deployment cost curve would start to move down. We will follow up on the result tomorrow. On EDGAR, there are no new filings after 6 Nov. TSLA merger progress is in today's TSLA brief and is not repeated here.

Key evidence

  • SpaceX website, 12 Nov: unveils the Texas Starport and Arizona Cochise supercomputing campuses
  • NYT, Bloomberg and Reuters confirmed the same day (12 Nov)
  • Texas Starport: campus of $24 billion or more with a self-built gas power plant, no public grid
  • Texas environmental filing, 11 Nov: about 35 turbines, about 748 MW
  • Arizona Cochise County: about $50 billion, 747 acres, up to 9 compute buildings
  • Arizona phasing: 4 phases of 1.5 GW each, or 6 GW at full build
Show 22 more
  • Arizona power infrastructure: 24 GWh of storage and about $3.6 billion of power infrastructure
  • Dry cooling and no industrial groundwater pumping (pre-empts backlash over water)
  • Cochise County public hearing scheduled for December
  • Texas tax abatement review scheduled for 9 Dec
  • Anthropic renewal still undecided (per brief of 12 Nov)
  • No new 8-K on EDGAR after 6 Nov: dollar figures and phasing not yet confirmed by the SEC filings
  • Zelensky statement, 12 Nov: the 100 mph (161 km/h) limit on military Starshield is back, systematic rather than random
  • SpaceX to Axios: this is false, nothing has changed
  • A US special envoy is arriving in Moscow at the same time
  • 24 Oct: Ukraine confirmed speeds were restored (stable above 400 km/h)
  • Same storyline as the UK telecom pause and the EU trust warning (earlier brief of 11 Nov)
  • United Airlines, 12 Nov: Starlink now on 50% or more of daily flights
  • As of 9 Nov: 689 aircraft, about 45% of the planned fleet and about 54% of daily flights
  • Regional fleets complete: CRJ-550 (100) and E175 (252)
  • A321 family 88%, 737 62%, 737 MAX 19%; widebody long-haul mostly 0%
  • United target for year-end 2026: about 64% of flights
  • United target for year-end 2027: full fleet
  • Starship Flight 15: launch window 06:45 SGT on 14 Nov
  • Booster 22 and Ship 42 (Gen 3), deploying 26 Starlink V3 satellites
  • About 14 orbits, flight of 22 hours or more, return the next day
  • First attempt at a full tower catch of both booster and ship
  • EDGAR: no new SpaceX filings after 6 Nov

Catalysts to watch

  • Arizona Cochise County public hearing in December
  • Texas tax abatement review on 9 Dec
  • Anthropic renewal decision
  • Finding tenants for 6 GW of new capacity
  • 8-K confirmation of the $74 billion-plus figures
Show 6 more
  • Fate of the allegations over the Ukraine Starshield speed cap: who is actually responsible
  • Progress of the UK telecom and EU trust storyline
  • United's widebody Starlink rollout schedule into 2027
  • Starship Flight 15 result: 14 Nov Singapore time
  • Success or failure of the first full tower catch
  • Starlink V3 deployment cost curve

Risks

  • Capex of $74 billion or more keeps the pressure on free cash flow
  • 6 GW of new AI capacity may struggle to find tenants if Anthropic does not renew
  • The Arizona county hearing could impose constraints
  • The Texas tax abatement could fall through
  • Political risk on the government and defence business is amplified by the Ukraine speed-cap controversy
Show 5 more
  • UK telecom pause, EU trust warning and Ukraine speed cap together make a cohesive geopolitical headwind
  • Aviation revenue is tied to the widebody rollout, so the upside is gated until 2027
  • Starship Flight 15 is the first attempt at a full tower catch and the catch could fail
  • The V3 cost curve waits on a successful orbital catch
  • Official figures are still unconfirmed in SEC filings: a reliability caveat

Sources 10

  1. SpaceX official website update, 12 Nov
  2. NYT, 12 Nov
  3. Bloomberg, 12 Nov
  4. Reuters, 12 Nov
  5. Texas environmental filing, 11 Nov (gas turbines, MW)
  6. Zelensky statement, 12 Nov
  7. Axios, 12 Nov (SpaceX denial on Starshield speed cap)
  8. United Airlines official tracker as of 9 Nov
  9. SpaceX EDGAR filings (no updates after 6 Nov)
  10. Starship Flight 15 mission plan